Projects

View our past projects below.

Westgold - Mt Henry Project 

Project Description: -12mm Mill Feed

Commodity: Gold

Project Status: Current

Location: Norseman

Duration: 2 month

Project Parameters: 4 Stage Crushing Plant 

Notes: 

Esperance Shire - Limestone Crushing Project 

Project Description: Limestone Road Base

Commodity:Limestone

Project Status: Current

Location: Esperance

Duration: 3 years

Project Parameters: Single Stage Impactor Crushing & Screening

Notes: 

Saracen – Thunderbox Project

Project Description: -25mm Mill feed.

Commodity: Gold

Project Status: Current

Location: 45km South Leinster WA

Duration: 6 months contract.

Project Parameters: Min 40,000 ton per month

Notes: Hard Rock crushing contract using 3 stage crushing plant to supply supplementary mill feed to increase project tonnages.

Saracen - Thunderbox Project - Fleet Setup
Saracen - Thunderbox Project - Supplies
Saracen - Thunderbox Project - Fleet Setup 2
Saracen - Thunderbox Project - Fleet

Metals X - Blue Bird Project 

Project Description: -12mm Mill feed.

Commodity: Gold

Project Status: Current

Location: Meekatharra

Duration: 14 months ongoing

Project Parameters: CSS 2 stage crushing plant.

Notes: 

Western Areas - Flying Fox 

Project Description: Contract Crushing for Ore Sorting Australia

Commodity: Nickel Ore

Project Status: Complete

Location: Flying Fox Mine Site - Forrestania

Duration: 6 Months

Project Parameters: Crush and Screen 170,000 ton low grade Nickel Stockpile.

 

West Gold - Higginsville 

Project Description: -12mm Emergency Mill feed

Commodity: Gold

Project Status: Completed May 2017

Location: Higginsville

Duration: 2 Months

Project Parameters: Mob Crush Screen 50,000 tons Emergency mill feed. Extremely Hard ore.

Notes: Less the two weeks from first Client contact to Producing mill feed onsite.

Central Norseman Gold Corporation LG Project  

Project Description: Crushing and Screening low grade ore at various locations for CNGC Mill Operations at 100,000t per month run rate. Various size fractions and various ore types are treated on site

Commodity: Gold

Project Status: Completed July 2016

Location: Norseman

Duration: October 2014 - July 2016

Project Parameters: Monthly 100,000t mine, crush and screen and transporting to the Rom via Road Train.

Notes: CSS has been a complete service provider for this project by being the preferred materials handling Contractor. This project was moving out of trail basis this year into full capacity production and CSS has been appointed as the preferred materials handling Contractor.

OMYA Calcite Project   

Project Description: Calcite separation from waste in OMYA Bathurst Quarry to upgrade quality of product delivered to the mill by using a mobile trommel. This needed to be done due to the amount offresh clay (Waste) in mined product.

Commodity: Calcite

Project Status: Complete

Location: Bathurst NSW

Duration: November 2015 till June 2016

Project Parameters: Monthly minimum 50 000t processed material per month.

Notes: This project commenced in November 2015 following on from trails carried out in Melbourne Victoria with this mobile trommel. OMYA Quarries had issues with feed stock material quality being presented which effected the final product. CSS as a solution based service provider put the concept forward utilising a mobile trommel to process and separate the waste. The initial trails have beensuccessful and it is envisaged that after a six month trial period, CSS will supply a bigger capacity unit on a contract basis to meet all the requirements for production and extend the quarry life by up to 10 years.

Golden Mile Milling Feed Crushing and Screen

Project Description: Complete Mill feed Crush and Screen project ROM Material processed to -20mm all in project.

Commodity: Gold

Project Status: Completed Mach 2016

Location: Kalgoorlie WA

Duration: November 2015 – July 2016mm 

Project Parameters: Monthly 30,000t to 50,000t ROM Material crushed and screened to -20mm all in final product

Notes: This project equipment consists of a primary Screen, and a secondary cone closed circuit delivering a -20mm product at 210t/hr run rate, with the capacity to increase to 350tph if enough feed stock is delivered to the ROM.

Anglo-Ashanti Tropicana Emergency mill feed

Project Description: Screen primary material to -8mm final product due to front end of milling circuit undergoing unplanned maintenance

Commodity: Gold

Project Status: Completed 

Location: Tropicana Gold, Goldfields WA

Duration: 16 Days from first contact

Project Parameters: 110 000t Screen to -8mmin 11 Days

Notes: This project showcased the alibility of CSS to be able to deliver a safe and professional turn key project in record time. From first contact by Anglo Gold, mobilisation of two 893 reclaimer screens, 4 loaders and 11 personnel, the completion of emergency mill feed took 16 Days, ensuring the client did not suffer any production down time through the Tropicana Mill. This project was completed without any safety concerns and to the highest standard.

Boral Quarries Deer Park

Project Status: Completed 

Location: Deer Park, Melbourne Victoria

Duration: 3 Months May 2015 - August 2015

Project Parameters: Quarry waste rock screening operation (mine, screen and stockpile)

Notes: CSS Pty Ltd was contracted to process a minimum of 40,000t/month waste rock, with final product for Council tip cover. CSS was responsible for complete contract scope, mining, processing and stockpiling of material. Mobile trommel was utilised for this project due to the nature of feed material and wet conditions. Project was completed on time and above client expectation of volume and quantity of product. 

Western Desert Roper Bar


Project description: Project Management and Plant Setup and productionincrease

Duration: 6 months January 2014 – June 2014
Commodity: Iron Ore

Project Parameters:Screen and Crush 240,000t/month Lump and Fines at 60% FE

Notes: CSS Pty Ltd was contacted by Peter Crooks, General Manager of Western Desert Resources in January 2014. Due to the onsite crushing contractor not performing and a dismal safety record, CSS mobilised Project Managers and Maintenance and Production teams to take over Crushing and Screening Project Management. Within 30 Days Production was increased by 60% and no LTI reported, after all logistics and management and safety systems were Implemented. This site was handed back to owner operator at the end of June 2014. 

Hope Downs 4 Rio Tinto


Project description: Project Management and Equipment Supply including Operations and Maintenance

Duration: 14 Months Dec 2013 – January 2014
Commodity: Iron Ore

Project Parameters: Crush Screen and Haul 340,000t/month lump and Fines FE 

Notes: CSS Pty Ltd completed this project sitting under another contractor’s banner project parameters, complete project management equipment hire maintenance and operational support. CSS personnel setup and executed the initial 1.8mt 6-month project professionally and on time to a strict rail and shipment schedule resulting in an 8-month project extension .

Frances Creek Iron Ore project


Project description: Complete crushing and screening site processing in JV with Barminco

Duration: January 2010 till January 2015

Project Parameters: Screen and Crush 200,000t/month Lump and Fines Iron ore, services consisted of project Management, equipment hire and complete circuit maintenance, CSS was contracted to operate and maintain site wet plant as well for a period of 6 months during initial start-up.

Notes: CSS Pty Ltd was contracted by Barminco at the start of the project, to turn a loss making project around where none of the project parameters had been met, over a period of 3 months the CSS team mobilised to site and restarted the project allowing Barminco to receive a 1 year project extension after the initial contract, when the Barminco Crushing and Screening contract finished, CSS in conjunction with the Owner operator project managed, and hired equipment to successfully run the Iron Ore operation till end of life in January 2015.

BHP Yandi 10MTPA


Project description10MTPA 5 mobile crushing plant operation

Duration: 3 Years

Project Parameters: Complete Project management on behalf of HWE Miningfor BHP Billiton Iron Ore 

Notes: Involved with Setup and execution of 10MTPA project, this included 5 crushing circuits producing -12mm final product,  72 project team was involved, from operators, maintenance personnel, and planners etc.

Contact us today for an obligation free quote for Western Australia's leading crushing solutions.

Powered by

iSeekPlant Logo